A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Work - Meeting contributes to This Process.

A Process happens in an organizational Context.
Context: The Project Leaves Blender

Objectives
* Remix / design and prototype a mid-size leaves blender.
* Evaluate its performance.
* Distribute a few prototypes to organizations local producers or through NGOs.

Description
A leaves blender is used to extract leaves concentrate, which can be of highly nutritional value.
Leaves concentrate is essentially a curd, made from leaves juice.

This process fulfills a Work order.
Order: Work order 319 due: 2021-05-16

Previous processes:

This Process:

Work Package 5 - Wrapping up and Document - Project or process documentation starting 2021-05-11 ending 2021-05-16

Documentation and reports, assembly and user manuals

Total budget of 1000$

WORK ETHIC REQUIREMENTS
# Work should be done transparently, allowing all project contributors to provide feedback and to contribute.
# Contributions without proper documentation are invalid.
# Documentation should be created progressively, during every work session, not at the end of a task.
# This task cannot be monopolized by any contributor, it is open to participation.
# Number of man-hours and budget are fixed. If more time is spent than planned and money to be paid surpasses the allocated budget, contributors involved in this task split the allocated budget in proportion to everyone's contribution.
# Contributions that do not reflect good work, that are inflated, or that are not properly documented can be redflagged by any contributor in this project, which can lead to the invalidation of the contribution. Repetitively misrepresenting work in logged contributions can lead to expulsion from project.

Working doc here
https://docs.google.com/document/d/1aY7cXj7ZX9juJ0NT3E-metR9oGrWvM8Cjb2vZdUsYw8/edit#

Input requirements:

Time Contribution Work - Meeting 10.00 Time - Hours

Meetings with others for coordination.

Time Contribution Work - Documenting 20.00 Time - Hours

Edit reports, assembly and user manual.

Output plans:

Document - Project or process documentation 1.00 Idea

Leaves Blender Testing, Reports and Manuals

Resources created:

Next processes: