A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Work - Meeting contributes to This Process.

A Process happens in an organizational Context.
Context: The Project Ventilator

Produce an open source design and prototype of a ventilator.

This process fulfills a Work order.
Order: Work order 304 , Information mining and Build lists due: 2020-03-31

Previous processes:

This Process:

Information mining and Build lists starting 2020-03-23 ending 2020-03-31

Input requirements:

Time Contribution Work - Documenting 1.00 Time - Hours
Time Contribution Work - Information mining 1.00 Time - Hours
Time Contribution Work - Writing 1.00 Time - Hours
Time Contribution Work - Meeting 1.00 Time - Hours
Time Contribution Work - Outreach-Marketing 1.00 Time - Hours
Time Contribution Work - Facilitation and coordination 1.00 Time - Hours

Output plans:

Document - Publication Brochure 1.00 Each

Resources created: