A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Work - Information mining contributes to This Process.

A Process happens in an organizational Context.
Context: The Project Spider rig

Create a spider rig

This process fulfills a Work order.
Order: Work order 284 , SpiderRig India due: 2019-05-31

Previous processes:

This Process:

SpiderRig India starting 2019-04-15 ending 2019-05-31

This is a fork for the project, adapted to India context.

documenting here
https://docs.google.com/document/d/1aqeWWQ-jc_D3fwcCy9ex2F_zSMdutxCwN_wmNGj3N_0/edit#

Input requirements:

Citation R&D report
Time Contribution Work - Office 1.00 Time - Hours
Time Contribution Work - Facilitation and coordination 1.00 Time - Hours
Time Contribution Work - Writing 1.00 Time - Hours
Time Contribution Work - Information mining 1.00 Time - Hours
Time Contribution Work - Documenting 1.00 Time - Hours
Time Contribution Work - Analysis and Strategy 1.00 Time - Hours

Output plans:

R&D report 1.00 Idea

Resources created:

Next processes: