A Process takes inputs and transforms them into outputs, and may be connected to other Processes in process flows. The work of Work - Meeting contributes to This Process.

A Process happens in an organizational Context.
Context: The Network SENSORICA
This process is connected to other processes to fulfill a Work order.
Order: Work order 245 for NRP remake 2017 initiative due: 2017-08-07

This Process:

Write the budget to NRP remake 2017 initiative starting 2017-07-29 ending 2017-07-31

Start from this preliminary budget
https://docs.google.com/spreadsheets/d/1ipkXSYTXnQAt_vqm3MUt10PlWjJ3nRxQsWmR0kVBHnQ/edit#gid=0

and propose one that is in line with a detailed Work Plan.

Input requirements:

To Be Changed Document - Presentation 0.00 Idea
Time Contribution Work - Meeting 50.00 Time - Hours
Time Contribution Work - Accounting and Finance 100.00 Time - Hours
Time Contribution Work - Documenting 100.00 Time - Hours

Output plans:

Document - Presentation 1.00 Idea