Planned Work: (Requirements are ordered by due date)

Business building work: 1.00 Time - Hours due April 21, 2016
Unassigned
Recruiting work: 1.00 Each due April 21, 2016
Unassigned
Office work: 1.00 Time - Hours due April 21, 2016
Unassigned
Outreach-Marketing work: 1.00 Time - Hours due April 21, 2016
Unassigned
Training self work: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
April 26, 2016 0.80 Time - Hours Done by Abran

During the meeting today we discussed the need of our sponsor to preserve its first to market advantage. SENSORICA is refining its interface with classical organizations and the issue of transparency and openness comes very often. I discussed with Tibi, who explained the problem to me, I am going to work on it.

Facilitation work: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
May 2, 2016 0.50 Time - Hours Done by Abran

Outreach to the Sensorica community regarding the request by our sponsor for selective openness. A lack of opposing arguments through email content is deemed as non-opposition of idea. Garnered some feedback supporting the idea and how it can be implemented.

Documenting: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
Oct. 18, 2016 3.50 Time - Hours Done by Tibi

Updated almost all the inventory of parts
https://docs.google.com/spreadsheets/d/1R5ld0w9aLhNUQL-zMrS9Wpo7-WhRpjzEib7I87G-bFI/edit#gid=0
Restructured the inventory spreadsheet.
Cleaned and organized the electronic components at the work station at the same time. It makes work less frustrating and more efficient, finding stuff better and knowing what we have in stock.

Administration work: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
June 27, 2016 0.80 Time - Hours Done by Tibi

Did some numbers crunching and analysis about project burn-rate, comparing the vibration/sound sensor and displacement sensor's actual dev time with predicted dev time, and sent this to the sponsor's project manager.
https://docs.google.com/spreadsheets/d/1aDBbqmyrRSRDJXOHEUY_Iw_vZO4NvVVlLOebp0l3yDY/edit#gid=350311137
I also set up the discussion for a request for another small project, about a 2 sensor device.

May 2, 2016 0.75 Time - Hours Done by Abran

Brainstormed to create a structure for making Sensor Network project selectively open. Fleshed the ideas out with outlines of tasks and processes that need to be completed. Results were put in a document linked below. Writing of the document were logged under the Documenting Task under the same process.

https://docs.google.com/document/d/1gXqCI4_ugfdTGqDZCUqSSs76fFY_e_xwmLzYgWK76vg/edit?usp=sharing

Writing work: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
May 2, 2016 1.00 Time - Hours Done by Abran

Created documentation formalizing the processes involved in making the whole Sensor Network project selectively open.

https://docs.google.com/document/d/1gXqCI4_ugfdTGqDZCUqSSs76fFY_e_xwmLzYgWK76vg/edit?usp=sharing

Information mining work: 1.00 Time - Hours due April 21, 2016
Unassigned
Training others work: 1.00 Time - Hours due April 21, 2016
Unassigned
Work events:
April 26, 2016 0.80 Time - Hours Done by Tibi

During the meeting today we discussed the need of our sponsor to preserve its first to market advantage. SENSORICA is refining its interface with classical organizations and the issue of transparency and openness comes very often. I explained the problem to Abran, who is going to work on it.

Meeting work: 20.00 Time - Hours due May 31, 2016

Scrum meetings at the partner's location, or between sensoricans, concerning the project.

Unassigned

Process context:

Pattern: Human resource management
Context: Sensor network
Order: Work order 211 due: 2016-04-21

Previous processes:

Next processes:


Process notes:

This is SENSORICA's overhead work, going into Miscellaneous for every feature or task from the sponsor's ERP.

This is about Outreach (find new talent), Orientation (show the new people around), Facilitation (help the new people integrate processes), Coordination (coordinate work among different participants) . Also included is the need for selective transparency as required by our sponsors.