Process: Milestone 3 Coordination and Facilitation to Conditions for PV characterization starting 2015-07-18 ending 2015-08-08

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Document - Conditions for project @Coordination and Facilitation 1.00 Idea due Aug. 8, 2015

Work

Planned Work: (Requirements are ordered by due date)

Work - Facilitation and coordination: 13.00 Time - Hours due Aug. 8, 2015

Organize meetings, communicate with participants, etc.

Taken by Tibi
Work events:
Oct. 16, 2015 1.00 Time - Hours Done by Jim

Filmed and uploaded two videos to show the fully assembled gimbal and Martinez board and micromanipulators.
https://drive.google.com/open?id=0B-s1IR1iOMsNZUdhcXpuNzBDNGc
https://drive.google.com/open?id=0B-s1IR1iOMsNeVhrM0xMZk9ZVjg

Sept. 18, 2015 30.00 Time - Hours Done by Bruce

Had a Workparty where we created a video and published it, to reestablish the momentum for the project.
https://www.youtube.com/watch?v=Vi5bh9IrOHs

Sept. 3, 2015 2.00 Time - Hours Done by Jim

Had a Workparty where we created a video and published it, to reestablish the momentum for the project.
https://www.youtube.com/watch?v=Vi5bh9IrOHs

Sept. 3, 2015 2.00 Time - Hours Done by Daniel

Had a Workparty where we created a video and published it, to reestablish the momentum for the project.
https://www.youtube.com/watch?v=Vi5bh9IrOHs

Sept. 3, 2015 2.00 Time - Hours Done by Tammy

Had a Workparty where we created a video and published it, to reestablish the momentum for the project.
https://www.youtube.com/watch?v=Vi5bh9IrOHs

Sept. 3, 2015 2.00 Time - Hours Done by Tibi

Had a Workparty where we created a video and published it, to reestablish the momentum for the project.
https://www.youtube.com/watch?v=Vi5bh9IrOHs

Aug. 13, 2015 1.50 Time - Hours Done by Thomas

Proposed a simple workflow for the software development as well as a common baseline to make contributions easier.

Aug. 12, 2015 0.50 Time - Hours Done by Jim

Had a google hangout with Thomas Vanesse to co-ordinate on project.

Aug. 12, 2015 0.50 Time - Hours Done by Thomas

Had a google hangout with Jim to co-ordinate on project.

July 29, 2015 0.25 Time - Hours Done by Jim

Meeting for the project and recorded it to share with the rest of the group.

July 29, 2015 0.25 Time - Hours Done by Tammy

Meeting for the project and recorded it to share with the rest of the group.

July 29, 2015 0.25 Time - Hours Done by Daniel

Meeting for the project and recorded it to share with the rest of the group.

July 29, 2015 0.25 Time - Hours Done by Tibi

Meeting for the project and recorded it to share with the rest of the group.

Process context:

Pattern: Change
Context: PV characterization
Order: Work order 165 for Conditions for PV characterization due: 2015-08-22

Previous processes:

Milestone 3 Outreach to Conditions for PV characterization starting 2015-07-18 ending 2015-08-08

Next processes:

Milestone 3 Write report to Conditions for PV characterization starting 2015-08-06 ending 2015-08-08


Process notes:

Make sure everything is running smooth, that people know what to do and when to do it. Assist participants with documentation, logging...
Make sure that the project stays stigmergic, so we can continuously swarm it, till the end.

13 hours are allocated to this, at 20$/hour, for a total of $259. If the participants log more time, they can chose to transfer it into equity for the commercial version of the device.