Process: Create Glass fiber constriction transducer - fabrication starting 2014-08-12 ending 2014-08-12

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Unplanned Production:

Work

Planned Work: (Requirements are ordered by due date)

Unplanned Work:

Work event: Work - Documenting 1.00 Idea Aug. 12, 2014 Done by Tibi

Updated the documentation and communicated it to the commnity

Citations

Method - Wet coating
Onhand: Chemical-wet coating - shaking
Cited: 1.00 Idea Aug. 12, 2014