Process: Design Micro Gym starting 2013-10-01 ending 2013-10-11

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Unplanned Production:

Work

Planned Work: (Requirements are ordered by due date)

Unplanned Work:

Work event: Work - R&D mechanics 24.00 Time - Hours Oct. 11, 2013 Done by Ivan

Process context:

Pattern: Generic R&D
Context: Aestuarium

Previous processes:

Next processes:

Make Micro Gym prototype starting 2013-10-01 ending 2013-12-31