Process: Access COVID Hardware prototype starting 2020-05-08 ending 2020-05-16

If you were logged in and working on this process, you would log your work on this page.

Outputs

Scheduled:

Design 1.00 Idea due May 16, 2020
Prototype 1.00 Each due May 16, 2020

Work

Planned Work: (Requirements are ordered by due date)

Work - R&D electronics: 1.00 Time - Hours due May 8, 2020
Unassigned
Work events:
May 19, 2020 3.00 Time - Hours Done by Tibi

Improved second prototype, added white LED light band, rewired everything and assed an electrical plug to the prototype https://www.youtube.com/watch?v=8zjZ65-5mMw&t=1s

April 26, 2020 0.75 Time - Hours Done by Tibi

Searched electronic components that could be used in the prototype, Adafruit for example. Documented options. Imagined a way to assemble the prototype.

Work - Documenting: 1.00 Time - Hours due May 8, 2020
Unassigned
Work events:
April 28, 2020 2.00 Time - Hours Done by Tibi

Created working doc, a few updates.

Work - Meeting: 1.00 Time - Hours due May 8, 2020
Unassigned
Work - R&D mechanics: 1.00 Time - Hours due May 8, 2020
Unassigned
Work events:
May 31, 2020 2.00 Time - Hours Done by Tibi

Finished the hardware prototype. Published and shared video.
https://youtu.be/d3NcbLqTMro

May 9, 2020 4.00 Time - Hours Done by Tibi

First mock-up / prototype. Play with some materials, get a feel about the shape.
Made video https://youtu.be/aAoFlDiZ9F0

April 30, 2020 6.00 Time - Hours Done by Tibi

Creates second mock-up / prototype.
This one looks better. Documented in working doc. See pictures.

Work - Shopping: 10.00 Time - Hours due May 16, 2020

Searching or buying materials

Unassigned
Work events:
May 1, 2020 1.00 Time - Hours Done by Tibi

Went to Home Depot to buy materials for the second prototype.

April 24, 2020 1.00 Time - Hours Done by Tibi

Online search of proper materials.

Usable Inputs

Space Office: 1.00 Area - square meters due May 8, 2020
Space Lab: 1.00 Area - square meters due May 8, 2020
Onhand: Space - Frederic D's lab 200.00 Area - square meters
Onhand: Space - Makxim's lab 100.00 Area - square meters
Onhand: Space - Phil's lab 25.00 Area - square meters
Onhand: Space - SENSORICA Montreal lab 250.00 Area - square meters
Used: Space - SENSORICA Montreal lab 8.00 Time - Hours May 4, 2020 by Access Covid
Onhand: Space - SENSORICA Robotics lab 1000.00 Area - square meters

Process context:

Pattern: Generic R&D
Context: Access Covid
Order: Work order 305 , Access COVID Hardware prototype due: 2020-05-16

Previous processes:

Next processes:


Process notes:

We are focusing at this moment on a hardware mock-up - alpha prototype. This will be used in a demo, to gain the support of local authorities and government.
We will continue to advance the design and prototyping once we have that support.

Document here https://docs.google.com/document/d/1BZuUhYca-ldk3OGl_YKMuq5mEr_FC-GZLjgrIaEXIp8/edit#